Project LEILAC has successfully started the commissioning process

Reducing CO2 Emissions

Daniel Rennie \ May 18, 2019

The commissioning activities over April has involved successful test firing the furnace burners, the testing of each process line, a furnace refractory dry-out, cold feed conveying, and extraction system testing.

On the 7th of May 2019, the LEILAC consortium partners and External Advisory Board met to celebrate the finish of construction with a ribbon cutting event at the LEILAC pilot plant. Supported by the European Union’s Horizon 2020 programme and extensive industrial backing, this event was a significant moment in the development of Calix’s Direct Separation technology, and the culmination of many years of hard work by all of the project partners.

The critical next steps for Project LEILAC involve “fingerprinting” the operation of the plant over May and June, including initial runs on lime and cement meal. These initial runs will significantly de-risk the technology and conclusively demonstrate its technical principles. The longer-term runs over the remainder of 2019 and 2020 will focus on extending the operational limits of the technology, as well as long-term studies on issues such as mechanical limits and fouling and corrosion, in preparation for scale-up designs for cement applications.

Calix is also pleased to announce that a new €1.5m working capital facility has been agreed with the Efic in support of Project LEILAC, which will support the project financing through to the end of February 2020.

Testing is now set to commence and start to validate the performance of the pilot, and a significant step in enabling Direct Separation to become one of the principal methods of capturing the carbon emissions from the lime and cement industries.

September 18, 2019 \ Reducing CO2 Emissions
BBC Podcast about LEILAC: Can capturing carbon buy us time to tackle climate change?

LEILAC team welcomed the BBC to the LEILAC pilot plant at HeidelbergCement’s Lixhe site. The visit was part of People

September 02, 2019 \ Calix Global Challenges
Introducing Anna Tran – Safety Health Environment and Quality Manager

Anna is the Safety, Health, Environment and Quality (SHEQ) Manager at Calix, overlooking health and safety across Calix’s local and

September 02, 2019 \ Reducing CO2 Emissions
Calix successfully demonstrates CO2 separation at Project LEILAC in Belgium

The LEILAC consortium is pleased to provide an update on the project since completion of construction in early May. Preliminary

Subscribe to receive information about Calix, News, Products & resources

Last Tweets

#marsisforquitters

Watch the full presentation of @phil_h_hodgson7, Calix Managing Director & CEO at #CO2NNECT2019

on Decarbonizing the Construction Industry
And find out how @ProjectLEILAC can help..

@CCSTechFacts
@GlobalCCS

#carboncapture

https://t.co/9go7sYzeWS

On this #Toiletday, we can't flush our responsibilities in term of sanitation
At Calix, not only we help improving the #sustainability of #wastewater treatment but we also support @WaterAidAus programs to facilitate access to sanitation and hygiene in the world’s poorest regions